Photo: Four people, two each on a timber carrier, lift stringer into place

Continued: Project name: Marten Creek

Once the stringer was winched across as far as it would go, it had to be lifted into place. Two timber carriers were used for this purpose

Bolts secured the stringers to the support logs.

The volunteers helped to construct and place 3 stringers to the bridge. The Forest Service Trail Crew were to finish the project in 2-3 days.

Photo: Laurie drilling hole for bolt

Photo: Laurie drilling hole for bolt

Photo: Thea walking the first two new stringers

Photo: Three stringers on bridge